Judgment Summary

  • Overview / Background: The appellant, a private consultancy firm, entered into a consultancy contract dated 26.05.2007 with the respondent statutory authority, under which professional services were to be rendered and payments released milestone-wise against invoices supported by reports approved as satisfactory by the client. A mobilization advance was paid and deliverables were submitted, but the balance claimed was not released, whereupon the appellant filed a suit for recovery of Rs.14,950,000/-. The suit was dismissed by the trial court and the dismissal was upheld in appeal, and the appellant preferred a second appeal before the High Court. The point for determination was whether the appellant was entitled to the remaining amount of Rs.14,950,000/- under the contract.
  • Key Point 1: The Court held that although the appellant was obliged to dispatch invoices along with reports of satisfaction, those reports were to be furnished by the respondent to the appellant, and admittedly no such report was ever forthcoming, while several invoices had nonetheless been processed and paid without it. No letter or response expressing dissatisfaction with the work was ever furnished, and the respondent, though entitled under the termination clause to terminate the contract if performance was found wanting, never exercised that option. The respondent's witness had limited personal knowledge, could identify no letter or reminder concerning the deliverables, admitted that no communication of dissatisfaction was made, and annexed no document to his affidavit-in-evidence. The respondents were accordingly estopped from raising the objection at a belated stage. The Court further held that the intentional relinquishment of a known right lay in the respondent's discretion to convey its dissatisfaction, which was never done, and such failure could only be classified as acquiescence; in the circumstances the respondent had a duty to speak and raise its concerns about the work tendered.
  • Key Point 2: On burden of proof, the Court held that once the appellant stepped into the witness box and exhibited the work done and the relevant invoices, the burden shifted to the respondent to satisfy the Court that the tasks undertaken under the contract were not satisfactory — this being the burden of proving a particular fact under Article 119 of the Qanun-e-Shahadat Order, 1984, whereas the initial and general burden lay on the appellant under Articles 117 and 118, and had been duly discharged.
  • Key Point 3: Elaborating the doctrine of acquiescence and estoppel by silence, the Court held that it was not open to the respondent to procrastinate over the issuance of the satisfaction certificate, and that the alleged dissatisfaction coupled with the lack of communication to the appellant could only be classified as deemed satisfaction, that is, acquiescence. Through its conduct — silence, and more particularly its omission to respond to the appellant's claims — the respondent caused the appellant to believe that the work done was satisfactory. Waiver or acquiescence being the intentional relinquishment of a known right or such conduct as would warrant an inference of relinquishment, mere inactivity will not ordinarily found an estoppel except where special circumstances give rise to a duty to speak and it would be unconscionable to deny the position thereby created.
  • Key Point 4: The Court held that the courts below had paid no heed to section 46 of the Contract Act, 1872, under which, where no time for performance is specified, the engagement must be performed within a reasonable time, what is reasonable being in each case a question of fact. No timeline having been stipulated for the grant of the certificate of satisfaction, the respondent could not withhold it indefinitely; the legal notice having been dispatched two years after submission of the invoices, that period could safely be construed as reasonable, and the courts below ought further to have deduced reasonable time from the contractual clause deeming the final report approved as satisfactory ninety days after receipt absent written notice of deficiencies.
  • Key Point 5: On the scope of second appeal, the Court held that although the High Court is ordinarily slow to interfere with concurrent findings of fact, this is not an absolute rule, and where the lower fora have misread, failed to read or misinterpreted the evidence and reached hasty or illegal conclusions, the evidence may be reappraised in second appeal. The trial court's view that the appellant had not satisfactorily performed its contractual obligations was found unfounded and unsupported by the evidence, and the present appeal was held to fall well within the narrow scope of section 100, C.P.C.
  • Final Decision: The appeal was allowed. The impugned judgment and decree of the appellate court were set aside and the appellant's suit was decreed in the sum of Rs.14,950,000/- with mark-up at bank rate, the Office being directed to prepare the decree accordingly.

Sections Included

  • Qanun-e-Shahadat (10 of 1984) — Arts. 114, 117, 118 & 119
  • Civil Procedure Code (V of 1908) — S. 100 & O. XLI, R. 31
  • Contract Act (IX of 1872) — S. 46